June 26, 2023
Green Mountain Electric Supply along with Southwire and Yusen Associates recently worked on a project with Benoit Electric. This project involved a solution that saved the customer numerous hours of labor. They were able to complete all 54 pulls in 2 hours, normally taking 10 people and 3 to 3-1/2 weeks to complete. Read below to learn more about the process.
The basic concept is parallel wire runs stacked on reels which are then mounted in an A-frame and shipped via flatbed tractor trailer direct to the job site. Once on site you unlock the reels and pull direct from the truck. In this case the job site required we remove (3) of the A-frames and transport them to the other side of the building where there was a second crew of men. Each reel is custom labeled with